04. June 2024

Rapid Route Cable Troughing System, TRU

Requirement

The Castleford section of the Transpennine Route Upgrade (TRU) required a durable, lightweight cable troughing system that could be installed efficiently on a steep embankment near the River Aire. Traditional concrete foundations were impractical due to installation time, environmental impact, and accessibility constraints. A sustainable solution was needed to reduce disruption and carbon emissions while ensuring long-term structural reliability.

Testing

To ensure the feasibility of the proposed solution, extensive material assessments and system trials were conducted. The ARCOSYSTEM®, made from pultruded glass fibre reinforced polymers (GRP), underwent durability and environmental testing to verify its resistance to extreme weather conditions, from -40˚C to +80˚C. The screw pile anchoring system, supplied by Anchor Systems, was evaluated for load-bearing capabilities and stability, particularly on uneven terrain. The testing phase confirmed that this combination would offer enhanced flexibility, reduced installation time, and superior longevity compared to traditional alternatives.

Solution

The Rapid Route ARCOSYSTEM® installation was successfully implemented, utilising Anchor Systems’ screw piles to eliminate the need for traditional concrete foundations. The elevated ARCOSYSTEM® cable containment system, supported on posts spaced up to six metres apart, significantly streamlined installation. The system’s bespoke steel bracketry provided adjustable height and directional flexibility, ensuring smooth navigation along the embankment. This solution not only optimised installation efficiency but also contributed to reducing carbon emissions by minimising material waste and site intervention.

Result

The 1,000-metre installation was completed on time with minimal disruption. The lightweight and adaptable system significantly cut down installation hours and carbon footprint, receiving positive feedback from J Murphy & Sons Ltd. By integrating innovative materials and efficient anchoring, the project successfully met all structural, environmental, and operational objectives, reinforcing Anchor Systems’ commitment to sustainable railway solutions.

Rapid Route Cable Troughing System, TRU.jpg
Rapid Route Cable Troughing System, TRU 2.jpg
Rapid Route Cable Troughing System, TRU 4.jpg
Rapid Route Cable Troughing System, TRU 3.jpg
IMG_2715.jpeg
20240505_052642560_iOS.jpg
20240505_052008791_iOS.jpg
20240505_045843246_iOS.jpg
20240505_051929516_iOS (1).jpg
20240505_051958461_iOS.jpg
20240505_045958706_iOS.jpg
20240505_050401413_iOS.jpg
20240505_051117105_iOS.jpg
20240505_051616232_iOS.jpg
20240505_052248646_iOS.jpg
20240505_052335776_iOS (1).jpg
20240505_052338534_iOS.jpg

Trusted by professionals. Backed by knowledge.

With decades of experience, Anchor Systems International delivers solutions that stand the test of time — no matter the soil, load, or location.

  • Extensive Technical Know-How

  • Load-Verified Anchoring Systems

  • Solutions for Rail, Civil, Utility & Green Infrastructure

  • Training & On-Site Guidance Available